3.4 Data Management and Archiving Group (DMAG) Staff and Budget


The Data Management Group Staff in FY96 included:

McCallum, Myron (Head, Data Management Group); Responsible for developing and implementing a data management and archiving capability for GPS data collected on UNAVCO supported field projects. Responsible for managing the office computing capability, including appropriate network connectivity and applications tools. Manages the group's budgets. Member of the UNAVCO Management Team.

Nienhouse, Eric (Software Engineer/Programmer); Responsible for providing support to a distributed user community for accessing and interpreting data collected on field projects. Archives field data, develops database tools, and develops strategies for evolving GPS data. Responsible for software development and support and providing new tools to the user community. Strong interaction with field engineering staff and user community.

Perry, Stephanie (Software Engineer); Responsible for developing and testing remote communications software, developing database tools, and strategies for evolving GPS data. Responsible for software development and support and providing new tools to the user community.

Roth, Ramon/Crawford, Scott (Systems Administrator); Responsible for support of both scientific and office computer operations. Maintains and monitors installation and upgrades of hardware and software, troubleshoots and repairs systems and network problems, and proposes and implements systems enhancements. Writes programs and scripts to increase system functionality.

Richardson, Vera (Archivist); Responsible for in-office support to the data management group by updating and maintaining archive data records while entering data into the archive. Consults with staff and properly transfers older data into the archive. Works with the archivist to improve database entry and report generating programs.

Table 3-1 shows funds budgeted and actual expenditures for data management support for FY96. Staff were budgeted at 2.62 FTE and were expended at 2.31 FTE and the overall budget was under spent by $46,612. The under expenditure was primarily in the staff area due to the loss of Ramon Roth, Systems Administrator, during the year and delays in bringing the Archivist onboard as soon as anticipated. Expenditures for consulting support under Purchased Services were higher than budgeted due to additional development work on the Archive Database and a significant increase in Web development work and implementation of products on the Web which was being supported within the Data Management Group during this period. The purchase of a new server was delayed due to the departure of Ramon Roth and questions about the most appropriate hardware for the systems upgrade. The RAID system was purchased and installed in FY96 but it was paid for from carryover funds and not the FY96 Data Management budget.

Table 3-1: Data Management Budget and Actuals for FY96

FY96 - Data Management Budget Actual

Salaries (Budgeted % FTE, Actual % FTE)

McCallum (50%, 58%)

29,429

34,195

Nienhouse (55%, 72%)

22,957

29,568

Roth/Crawford (55%, 62%)

28,967

29,004

Richardson (52%, 39%)

14,674

10,524

Software Eng/Prog II (50%, 0%)

29,037

0

Total Salaries

125,064

103,291

Benefits (45.8%)

57,279

47,307

Materials and Supplies

General Materials

5,500

2,681

Network Equipment

8,000

6,057

UNIX Server Upgrade

2,000

1,099

PC Upgrade

1,785

0

Electronic Stores Chargebacks

600

227

Books

300

249

Journal Subscriptions/Dues

150

107

Total Materials and Supplies

18,335

10,420

Purchased Services

Consulting Support (Pierce for 6 months x 35 hrs/wk)

48,304

59,658

Computer Maintenance

5,000

4,814

Applications software

3,500

3,252

Operating System software

2,000

1,637

Long-distance Phone

4,586

5,946

General Services

2,000

2,366

Training

1,000

0

Copier Usage

700

683

Freight

400

190

Advertising (1 paper)

400

0

Postage

355

58

Express Mail

100

315

Total Purchased Services

68,345

78,919

Travel

Domestic Travel

1,500

5,825

Local Travel

100

0

Total Travel

1,600

5,825

Equipment

Server

13,000

2,532

Total Equipment

13,000

2,532

Total Costs

Total Direct Costs

283,623

248,294

Indirect Costs (29.8%)

84,520

73,237

Total

368,143

321,531

Table 3-2 shows the FY97 budget for the newly organized Data Management and Archiving Group (DMAG) headed by Chuck Meertens. Under this new group, software development work related to GPS data translation (e.g. from vendor-specific receivers to RINEX), editing, and quality control previously supported within the Development and Testing Group was moved to DMAG. This work has been performed by Lou Estey on a consulting basis and shows up under Programming Services under Purchased Services. Lou will be brought on as a full time staff member in FY97 if budgets permit. The overall DMAG budget shows increased support for data entry into the archive, including finalizing data entry tools, and for development of several of the archive tools previously discussed, e.g., map and temporal interface. This increased level of activity plus the addition of the data translation, editing and quality control software development results in an overall 1.64 FTE staff increase from the FY96 actual FTE's. Purchase of the Digital Linear Tape system was deemed a high priority by the Steering Committee and is included in the FY97 budget. The increased staff plus purchase of the DLT system result in a budget increase from FY96 to FY97 of $22,507, or an increase from actual expenditures from FY96 to FY97 budget of $69,119. The subcontracts to the University of Miami and University of Texas at Austin for recovery of pre-92 data are not shown in this budget but appear in the summary budget discussed in section 6. All other budget elements are nominal and self explanatory.

Table 3-2: Data Management and Archiving Budget for FY97

FY97 - Data Management and Archiving FTE Budget

Salaries

Meertens

0.50

30,766

McCallum

0.50

27,700

Nienhouse

0.90

35,900

Richardson

0.50

13,143

Wallhaus

0.75

21,492

Total Salaries

3.15

129,001

Benefits (47.3%)

61,018

Materials and Supplies

Data Management PC

2,750

Memory Increase for Archive Server (64 MB)

2,000

Optical Media Reader

1,200

ISDN Line Hardware

1,200

General Materials (replacement parts, cables, etc.)

1,200

Floppy Disks and Computer Supplies

1,000

Office Supplies, Copier Paper, Toner

1,000

Serial Port Expander

800

PC Tape Back-Up and Tape Media

500

Distribution Media (4 mm and 8 mm)

400

Optical Disks (10 $35 each)

350

Journal Subscriptions/Dues

200

Total Materials and Supplies

12,600

Purchased Services

Programming Services (Oracle database development support)

0.80

49,300

Compiler Licenses

5,200

Oracle Software (license and maintenance)

3,000

Copier Maintenance (UN Bldg., $250 per month)

3,000

Archive System Maintenance (CPU, DISK, and PCs)

2,500

Seamless Database Access Software

2,000

Software for Tape Storage System (DLT)

2,000

ISDN Line Monthly Service

1,200

Monthly Service for Two Modem Lines for Archiving

1,200

Operating System software

1,000

Long-distance Communications (phone and pager)

1,000

Monthly Service on Modem Lines (2 lines for Data Management)

1,000

Training Courses

1,000

Freight, Postage, Express Mail

500

General Services (consulting support, etc.)

500

Total Purchased Services

74,400

Travel

Domestic Travel (3 trips at $900/ trip)

2,700

Local Travel

100

Total Travel

2,800

Equipment

Tape Storage System (DLT)

35,000

Total Equipment

35,000

Total Costs

Total Direct Costs

314,819

Indirect Costs (27.10%)

75,831

Total

3.95

390,650


1996 Annual Report - 23 SEP 1997

[Next] [Previous] [Up] [Contents]