UNAVCO Home
   |    |   |  
Promoting Earth science by advancing high-precision techniques for the measurement of crustal deformation.

· Publications & Reports · Brochures · Community Bibliography · Periodic Reports · Proposals · Staff Publications · Workshop Publications
Draft PBO Proposal

Standing Committee Preliminary Report

To: jdaviscfa.harvard.edu, wprescottusgs.gov
cc: Paul Segall (segallpangea.Stanford.EDU), Paul Silver (silverdtm.ciw.edu),
        "Duncan Agnew" (agnewbilby.ucsd.edu),
        "Mark Simons" (simonscaltech.edu), "Sue Owen" (owenterra.usc.edu),
        "William Holt" (wholthorizon.ess.sunysb.edu), mikejucar.edu,
        shiverucar.edu
Subject: Standing Committee Report on First Draft
Date: Tue, 30 Jul 2002 07:41:14 -0700
From: Frank H Webb (fhwcobra.jpl.nasa.gov)

Will and Jim,

The PBO Standing Committee recognizes the need for early and quick
feedback on the PBO proposal and are submitting this first report
summarizing our initial input on the first draft of the PBO proposal.
While there are issues due to the proposal being in its beginning stages
and several committee members being partially available or unavailable
for comment, this initial report is being forwarded along to UNAVCO,
so that the proposal team can get some initial feedback.  The report is
broken into three parts consisting of general comments, specific replies
to the 8 questions posed by Jim Davis, and specific comments on the text.

Also, we would still like clarification on the following questions.  I know
that we discussed some of them last week, however, an updated electronic
response would be helpful to document the issues.

1. The proposal schedule - When do you intend to submit it to NSF and
what is the schedule for reviews between now and then?

2. The intended audience - Who is the audience?  What is the depth of
detail that they expect?  Do they expect the focus to be on science,
management, and/or cost?

3. What is your expectation of the scope and depth of the proposal?

4. Could we get a budget that is broken down by work force?

5. Could we get a master schedule for the tasks involved?

6.  What is your expected funding profile?


Sincerely,

Frank

-----------------------------------------------------------------------------
General Comments:

The proposal is considered to be a good start. However, its flow is
somewhat uneven and it could be greatly improved by laying out in the
beginning the science rationale for the observatory and how that rationale
maps into the requirements. The drivers and rationale for the technical
approach, schedule, and management should flow down from these higher
level requirements.  These should then be used as the basis on which the
costs are estimated.  A plan and schedule on which these cost estimates
are based should be developed, including a high level work break down
structure (WBS) for the proposed effort and better costs justification.

In the context of the bugdet, the proposal team should do what it takes
to preserve the science goals of PBO in this early planning stage. The
budgets should be scrubbed in order to preserve these goals and determine
the level of descope, if any, of the project.

There is a sense that essentially only Mike Jackson is working on
the proposal at what seems to be a best efforts basis.  This would
be inadequate given the importance of the proposal and size of the
request.  It seems very risky for UNAVCO Inc. to accept what seems to
be a relatively high level of uncertainty in the costs and put out a
proposal. One risk is that they will not make a credible argument for the
project, which could result in it not being funded.  And, if it is funded,
it has the risk that UNAVCO will not be able to deliver at the proposed
cost and the first project of the corporation will have to be descoped
or canceled due to poor costing and planning.  More resources should
be applied to this very important project, especially, in the area of
planning and cost estimating.

Central control of the implementation seems reasonable given the
complexity of the implementation and is key to controlling the project
and the costs.  The plan and processes for how this management will be
responsive to the community input needs to be defined.

The omission of any reference to existing networks, their roles in PBO,
and experiences learned from them is a major weakness.



Specific responses to questions:

1.  Evaluate whether the current PBO facility plan, as outlined in the draft
proposal, has a high probability of meeting the community's observational and
science goals for PBO.  If not, then please be specific as to why.

	No. It proposes a descope in the numbers of GPS and strainmeter
	stations stating cost as the reason.  The costs are not well
	enough documented to determine how credible they are and if
	descoping is necessary.

	In addition, the decision making process for descoping and
	prioritizing is not defined.

	The role of the Regional Scientist is confusing and needs to be
	better explained.


2. Evaluate whether the proposal is targeted to the right audience, including
geo-scientists but also scientists from other disciplines and educated
non-scientists (such as members of the National Science Board).  Are there
technical terms and concepts that need further explanation or that could be
omitted without loss of meaning?

	No.  The proposal needs to address how the PBO will help to
	answer significant questions. The link needs to made as explicit
	as possible.

	There ought to be a page or two (as an appendix) on what
	these systems are, how they work, and what they measure--and
	probably another page or two on what a plate boundary is and
	what happens there. The geoscientists will skip it, others
	will be grateful. Think Scientific American level. The focus
	of the text on monumentation will seem bizarre to some readers,
	and needs to be justified.

	As written, the flow of the text is somewhat uneven in that it
	has in some places too much detail and others too little.

3. Evaluate whether the PBO plan is flexible enough to allow lessons learned
from the early years of operation to be factored into later implementation
plans.

	There is not enough detail to make this assessment.  As a
	related note, the proposal does not indicate how it has applied
	the lessons learned from previous network installations to this
	project.  The relevance of these lessons and the costs associated
	with the tasks in the other projects should be assess and compared
	with the existing project.  For what appears to be a relatively
	complex deployment and operation for implementation, it is not
	sufficient to merely assert that the costs are understood and
	present average station costs without some data or justification
	on the assumptions that go into those costs.

	There is concern about rigidity from the regional boundaries.
	Given that something like this is unavoidable, it would be
	preferred that these followed tectonic boundaries rather than
	state lines (perhaps a tectonic approximation to state lines?).


4. Evaluate whether the allocation of resources is optimal for the PBO science
goals, e.g., number of continuous GPS stations vs. borehole strainmeters, or
number of backbone GPS stations vs. clusters.  Does the proposed facility
address the highest priority plate boundary zone questions?

	There is not enough detail to make this assessment and in some
	sense it is late to be raising these questions. On Some Pre-PBO
	funds were allocated to address this and simulation studies
	may be performed in August to try and optimize PBO station
	deployment. Unfortunately this should have been done a long
	time ago.

	Additionally, we may never really know until afterwards. Station
	distribution will constantly evolve as sites are permitted and
	deployed, and areas of interest are found to be too expensive
	or impossible to build in. In the proposal, the point should be
	made that the community has spent a lot of effort to try to make
	this the case--several well-attended meetings. So it is pretty
	close to what we think is optimal, whether it actually is or not.

5. Evaluate whether the data archiving and data products plans are adequate to
meet the needs of individual investigators.  If not, how could it be
strengthened?

	In general, yes.  Though, the assumptions behind the proposed
	plans should be explicitly stated.  How many individual
	investigators are expected? What products do they want? Raw
	GPS? Tropospheres? Station velocities?	How will they interact
	with the system? Interactively via the Web or from the command
	line in some automated script?

	There was a concern that the need for two archive centers
	was not justified.  The availability and cost of existing
	commercial capability for mirroring big datasets at separate
	sites should be considered as an alternative.  Nothing we do
	is "mission-critical", hence we can afford to have occasional
	1-day outages, also--except right after an earthquake (or the
	week before AGU). This, and the fact that most of the data do
	not change once collected, ought to make the task of getting
	backup cheaper.


6. Evaluate whether the implementation schedule is realistic and
achievable.

	No. The schedule is too simplisitic and optimistic for the
	reconnaissance, permitting and deployment.  Even though permitting
	is flagged as having great uncertainty, the proposal gives the
	sense that it will be easily dealt with and that the capability
	to construct sites will control the schedule (and implicitly
	the costs).  This is at odds with the lessons learned from
	previous deployments of large GPS networks.  More detail needs
	to be provided to justify why the reconnaissance and permitting
	will not be the critical path in the implementation and why this
	will not impact the average cost per site.

7. Evaluate whether the staffing levels are realistic and sufficient to
accomplish the science goals of the PBO facility.

	May be not.  The staffing levels are reported in $ and not
	level of effort or FTEs and are not linked to a work breakdown
	structure (WBS) that clearly shows the tasks and the workforce
	and other direct costs (ODCs) required.  This suggests that the
	staffing levels are in part driven by trying to meet a cost cap
	and were not estimated based on the level of effort required.
	More justification of the costs would make it easier to evaluate
	the costs.

	There is some concern that the borehole strainmeter effort has
	a lower level of staffing. There is an 8:1 ratio of numbers of
	sites, but I think this may be more than counter balanced by the
	time needed at each site and the greater involvement that will
	probably be required of PBO staff in the process. The relative
	levels at least need to have serious thought, as part of the
	overall budget planning.

	In addition, the budget contains no  administrative staff for
	staff support.	Some dedicated staff will be probably be needed
	for general support, processing shipping paper work on all of
	the equipement that will flow through the facility, site permits,
	data entry, etc.

8. Advise as to whether there should be a further reduction in the number
of GPS and/or strainmeter stations in order to create a 10% management
reserve to meet future contingencies.

	The need for this level of reserve is not argued in the proposal.
	Some reserve is certainly necessary given the high uncertainty
	in a number of the tasks and activities.  The reserve strategy
	and the proper level of reserve need to be argued and justified,
	and applied at the WBS element level.

	If the reserve strategy is to reduce the number of sites this
	needs to be spelled out since it will have an impact on the
	scientific return of the network. For excample, as sites start
	going in the ground, the distribution of those sites begins to
	define the science return from the network.  If you know all
	of the possible site locations up front (that is they are all
	permitted before installation begins), the installations can be
	prioritized and the sites built such that if the project needs
	to be descope for lack of funds, the last sites that were to be
	built were the lowest priority. In reality, it is doubtful that
	construction will wait until all of the sites are permitted in
	exactly the `right' locations or that all of the sites permits
	will be approved in just the right order.  Rather it may be that
	sites will be built as they are permitted and the permits will
	come from as close to the plan as possible.




A compliation of specific comments from committee members:

Text and Figures -

	p. 3	Why is PBO adding met. packages to provide "an estimate of
	GPS derived tropospheric water vapor over the entire PBO region"?
	What science requirement is this responding to?

	Where is the science justification for the 100 field receivers?
	Why do we need to buy, warehouse, maintain, etc. this equipment?

	p.6 oblique views of pie charts are not helpful.  Also, it is
	not clear to me what the point is of showing how the relative
	amounts of the budget are whether or not they are shown as pies.

	p. 7 "Based on proven and accepted project management principles."

	p. 9 Regional scientist role statement needs to be tightened up.
	Why do you need a field engineer reporting to a regional
	scientist, who reports to a UNAVCO regional engineer? Fig. 2.3

	You should consider not having the Campaign engineer coming on
	line until later in the program after some number of stations
	have been installed.  In fact the after all have been installed,
	the campaign engineer could replace the backbone engineer.

	Fig 2.3 should be made bigger and show, what I assume to be,
	the flatness of the management structure. It looks as if it was
	made to fit the formating of the page.	Same for Fig. 2.4.

	p. 11 The site selection process is controlled by a sensitivity
	analysis.  Who does the sensitivity analysis?  How is that
	funded? What is it?  How much detail? Is this a full time
	person testing hundred's of scenarios per week?  How are issues
	resolved? Fig. 3.1 needs more arrows indicated the knott of
	checks that are being performed.  Every box is an approval gate.

	The description of the site selection procedure is to simplisitic
	given the knowledge of the difficulty of site selection and the
	criticalness of it to the overall project success and costs.

	p. 12 Who are these `constituents' that the regional scientists
	represent? The RS roles and responsibilities and authority need
	to be clarified.

	Figure 3.1: The basis for the siting plan should primarily be
	the reviews from the 2000 Workshop, not the earlier White Paper.

	p. 13 The statement "Station permitting and the permit approval
	process dominate the time and uncertainty in predicting the rate
	of station construction, limits the ability of the stations to be
	scheduled for construction, and thus controls the eventual rate of
	network deployment" should also include the effect on the costs.
	And how is this cost uncertainty budgeted? The stated plan seems
	somewhat simplistic and does not seem to incorporate the lessons
	learned by SCIGN and others.

	p. 14 The bulk permitting process described at the top of the page
	has been tried before.	Numerous problems exist between local
	and angency level control, and the need to pay the agencies for
	services such as biological screening, etc.  SCIGN's experience
	was that permitting can be very slow for large agencies, even
	when someone from the agency sits on your coordinating board.

	p. 14 Bullet 5, What if the owner wants us to pay a lease? What
	then?

	p. 14 Should not an attorney for UNAVCO Inc. develop the land
	use agreement (LUA)?

	p. 15 The plan of the Regional Engineers working to a fixed
	schedule published by the Director sounds very optimistic and
	inflexible to the dynamic scheduling and environment that may
	be likely to exist.

	p. 15, Sec 4.1. The regional engineer description reads like
	a general contractor. Why is the Regional Engineer acting as
	the general contractor? Why isn't the installation contractor
	responsible for his own schedule and supplies?	Why is UNAVCO
	seemingly warehousing everything and micromanageing the
	construction?  What expertize do they have in that?

	It reads like a management structure is being set up where
	UNAVCO is too much in the middle of making decisions at a
	very low level for its subcontracts.  A problem is that the
	drillers and the station installation subconstracts, for example,
	will be dependent on UNAVCO delivering on schedule a schedule,
	equipment, construction permits (not LUAs), Health and Safety
	reports, etc. which the subcontractors will have to work
	into their schedule with their other clients.  This puts the
	cost risk on UNAVCO and I don't see the rationale for this.
	Also, it requires a much higher level of coordination among
	all parties than would be needed if the installation contractor
	were responsible. Why not put the reponsinility for coordination
	of the contractor's activities on the contractor and let them
	propose a schedule that the UNAVCO contract manager (Regional
	Engineer) approves?

	Are the drilling and installation teams different and do they
	work at different times? That could cause a coordination and
	scheduling problem.

	p. 18 Why 1-2 weeks before operational?  Sounds arbitrary and
	counter to the well planned executed implementation that is
	being suggested. Should it not be 1-2 days?  Why not?

	Fig. 5.1 Get rid of the yellow gradient background unless it
	means something?  Add a time line to this figure.  Also, on other
	figures, the background colors, if they don't add anything to
	the content and message, should be removed.

	p. 19 What PBO requirements dictate the receiver requirements?
	For example, why ethernet? What if it costs too much, can we
	live without it? Sounds like a desire and not a requirement.

	p. 22 Why is UNAVCO Inc. purchasing the components and shipping
	them off to someone else? Doesn't this add costs such as handling
	and additional shipping costs? Are you envisioning a cost savings
	from no overhead by the subcontractor?  Why not write that into the
	subcontract rather than take on the logisitical expense of being
	a parts distributor?
--------
Budget -

	There seemed to be no budget for administrative staff for staff
	support.  Some dedicated staff will be needed for processing
	shipping paper work, site permits, data entry, etc.

	The need for level of reserve is not argued in the proposal.
	Some reserve is certainly necessary given the high uncertainty
	in a number of the tasks and activities.  The proper level
	of reserve needs to be argued and justified at the WBS level.
	My gut feeling is that 13% may not be enough.

	There is concern over the credibility of the cost estimate. In
	particular, it was somewhat premature to be descoping the science
	already on the first draft of the proposal.

	A cost comparison table should be developed and perhaps included
	for GPS and strainmeter stations based on the known/estimated
	costs from existing networks and showing their estimated cost
	for PBO. The table should be broken down by distance and type
	of station, such as Alaska, urban, remote, etc.

        The choice of equipment design,  3-component vs. 1-component,
        and the maturity seemed to be unresolved and contributing to
        the cost uncertainty. This needs to be resolved.


Processes -

	Station distribution maps (Dots Maps) - There needs to be some
	process where dots are translated to specific sites.  A strategy
	needs to be developed regarding the assumptions that can be made
	with respect to moving sites around for scientific reasons and/or
	cost control.

	Having lots of oversight committees passing judgement on whether
	or not this site or that site should be built and how should
	be avoided. The proposal team should consider developing a
	requirements document.	This document should be both specific
	enough about the mapping of the science goals and priorites to
	the observations that it could be used though out the project
	life to provide guidance to the field engineers, etc when making
	decisions that affect the quality of the science, but should
	not be so specific that it is unuseable.

	The PBO Director seems to be written in as a micro manager and/or
	doer of nearly all tasks.   This needs to be clarified.

--------
 Figure 3.1: The basis for the siting plan should primarily be the
 reviews from the 2000 Workshop, not the earlier White Paper.

 Figure 3.3: This flowchart is actually more difficult to follow than
 the bulleted description on the next page; I'd omit the figure.

 Section 3.4: It is not clear to me that it is a good idea to use the
 borehole casings as GPS monuments; and if this adds to the complexity
 and time spent finding sites, it may not save much money compared to
 building a GPS monument.
	On the positive side, I think the plan for permitting makes good
 sense, especially hiring some professionals (but is this really part
 of what an engieering firm does, or are there more specialized groups?).

 Section 4.2: The breakdown into construction phases is very good. I found
 the monumentation discussion confusing: a DDB (deep-drilled braced)
 monument will be used, except that in bedrock a SDB (shallow-drilled
 braced) will be used, and in unconsolidated material a concrete pier:
 this seems like a contradictory set of statements. (I also do not think
 the concrete pier should be called deep anchored, but that is a separate
 technical matter).
	For a strainmeter installation, grout is placed into the hole, not
 pumped.
	It is not completely clear to me that there has in fact been a
 community consensus on what should go into boreholes: the most thorough
 discussion I am aware of came from the ad-hoc strainmeter group at
 the Fall 2001 Earthscope meeting, and I'd hardly call this a community
 effort.

 Section 4.3, para 1: meteorological not metrological; and what is "this"
 in the last sentence?

 Section 4.3, para 2: wind power seems like an invitation to high
 maintenance.

 It is not necessarily less expensive. Construction and maintenance costs
 may offset any savings over other alternatives.  The windmill should
 be collocated away from the antenna, requiring power to be run some
 distance in a buried conduit.  It will need to be firmly attached to the
 ground with sufficient batteries to survive low wind days. In addition
 it adds siting requirements that are more restrictive, increasing the
 recon costs and influencing the network topology.


 Section 5.2, para 2: Full-scale production of GPS systems, or purchase?
 Section 5.2, para 3: State that the 100 recivers will be for survey-mode

 Section 5.3: Figure 5.2 is purely decorative: omit it.

 Section 5.4: The list of communications options seems odd in a couple of
 ways. One is that StarBand is not really meant for data communications (as
 opposed to consumer Web access), so I am not sure this will work. The other
 is that if satellite won't work, it is difficult to picture cell-phone as
 a backup.

 Though UNVACO has tested StartBand, I believe that this was boot legged
 on a consumer account, not an operational, business account. There may
 be hidden issues with their support of PBO's activities.

 I agree that the choice of cell phone seems odd the way it is presented.
 Also, while cell phone rates are low for consumers, businesses pay a
 significantly different rate, and the rate structures change frequently.
 Hence, the cost of cell phone is not well constrained, but seems costly.

 What about CDPD?

 Of course, of all the sections, this one is the most ripe for integration
 into the overall effort: USArray has to deal with telemetry too.

 Section 5.6: Again, it is not clear what type of monument will be
 used in which circumstances. I do not think the concrete pier is the
 "emerging choice of the GPS research community". (I did mention this
 to Mike Jackson and he plans to change it).

 Again, the proposal needs to better justify its plans and decisions.


 Section 6.2: It is not clear to me how th UNAVCO Facility will pre-test
 strainmeters, or that they are the right group to do so. This is the first
 of a number of cases in which what is right for GPS is carried over to
 a quite different measurement system.

 Section 7.2: A positive note: I like the data plan. One implication
 is that the Regional centers will not in fact store data onsite for very
 long, so they can be quite modest in scope.

 Section 7.3, last para: for my taste, this has too much detail about
 the software especially relative to the amount of detail presented on
 other, more significant elements of the project.

 Section 8: As indicated, it is not self-evident that the IGS model will
 work cleanly for strain data, at least at first. I don't want to be too
 tedious on this, but have to point out some differences between GPS and
 strain:
 	*)Raw GPS data (carrier-beat phase) are very structured: that is,
 they result from quite substantial processing of a heavily-engineered source
 signal. This makes automated processing easier.
 	*)GPS data are highly redundant. A day of 30-second data from N sites
 produces about 1.e5N values/day; the number of values out of the processing
 is more like 500 (orbit and EOP) plus 50N (position and troposphere): about
 1000:1 compression. For strain data there is no obvious equivalent compression.
 	*)And, many fewer man-hours have been spent developing software for
 dealing with strain data. For the old-timers, remember hand-editing cycle
 slips?
 	The upshot is that the idea (valid for GPS) that there are standard
 processing and products, just waiting to be implemented, is still a goal for
 strainmeter data. The proposal seems to assume that the state of play in
 the two areas is equivalent.

 Section 8.1: Who will decide when specialized datasets should be made
 available?

 Section 8.2: There is an ambiguity between how often solutions are produced
 (daily) and their latency (delay after real time). Latency of 1 day is
 useful for spotting problems (but for this the analysis can be rough),
 and after the occasional large earthquake (so, once overy couple of years
 at most); but on almost all days, it is not scietifically important. If
 there is a tradeoff between latency and completeness/quality, I'd go for
 the latter: there should at least be (as in global earthquake products)
 a range of products produced with differing latencies.

 In addition, what science goal/requirement or technical problem is
 driving the need for low latency?


 Seciton 8.3: It is stated that the Analysis Center Coordinator needs to know:
 	"The ACC will be a full-time positionn with the incumbent having
 a strong geodetic background with a detailed understanding of strainmeter
 error correction, GPS analysis strategies, and the application of
 reference-frame constraints to GPS solutions."
 	Perhaps I forgetting someone, but there appears to me to be
 exactly one person who could meet these requirements, and John Beavan
 seems very happy in New Zealand.

 Section 9.2: I'll raise again the question of what priority to give
 overseas projects: low, or none? Either will need to be justified.

 And the bigger issue of what process is used to decide on the priority
 for any project?  What will be the demand to use these receivers once
 we have 1200 installed around western North America? Who will use them?
 Is this the right number of receivers? Will not PI's have their own?
 This reminds me of the original operating mode for UNAVCO.


 Section 10 (or maybe elsewhere): do we have to promise to advance K-12
 education? This does seem unlikely.


Last modified Tuesday, 08-Nov-2005 02:34:51 UTC

 

Home | About Us | Contact Us | Support | Search | Facility | PBO | Education & Outreach

Comments: webmasterATunavco.org
© 2009 UNAVCO, Inc.